As this week starts, rough inspections have just finished up. The installation of drywall and cabinets begins!

With wiring and plumbing signed off we install insulation


Drywall is now covering what was just the wooden frame of the house


Cabinets go in next. This is the beginning of the end of this project!


Next we will be templating for granite counter tops...